Don’t Force It: UK Supreme Court Confirms Force Majeure Does Not Require a Party to Accept Non-Contractual Performance
Don’t Force It: UK Supreme Court Confirms Force Majeure Does Not Require a Party to Accept Non-Contractual Performance
The UK Supreme Court in RTI Ltd v MUR Shipping BV has unanimously held that, as a general point of principle, parties to a contract cannot be prevented from relying on a force majeure clause if they refuse to accept non-contractual performance by their counterparty. The judgment of 15 May 2024 reaffirms the English courts’ strict contractual approach to interpreting force majeure clauses in commercial agreements impacted by sanctions and increases commercial certainty for parties seeking to rely on such clauses.
In June 2016, shipowners MUR Shipping BV (“MUR”) entered into a contract of affreightment with RTI Limited (“RTI”) under which MUR would make monthly shipments of bauxite from Guinea to Ukraine. RTI agreed to make monthly payments to MUR, which the contract expressly provided would be in US dollars. The contract contained a force majeure clause, providing that an event or state of affairs could only be a force majeure event if it could “not be overcome by reasonable endeavours from the party affected” (emphasis added).
In 2018, RTI’s parent company was sanctioned by the US Treasury’s Office of Foreign Asset Control, rendering RTI, its majority-owned subsidiary, subject to the same restrictions. At the time of the Supreme Court judgment, it was common ground between the parties that it was highly likely US sanctions would have caused difficulties and delays in RTI making payment to MUR in US dollars. MUR claimed that the effect of the sanctions imposed was a force majeure event excusing it from performance.
RTI rejected MUR’s force majeure notice and offered to pay MUR in euros, and to bear any additional costs or exchange rate losses suffered by MUR. MUR rejected this offer. RTI then asserted that MUR could not rely on the force majeure clause as, in rejecting RTI’s offer for payment in an alternative currency, MUR had not used reasonable endeavours to overcome the sanctions-related event.
RTI commenced arbitration proceedings against MUR for breach of contract. The arbitral tribunal ruled in favour of RTI, finding that MUR had not satisfied the “reasonable endeavours” proviso of the force majeure clause in rejecting non-contractual performance of RTI’s payment obligations. MUR appealed this decision to the High Court.
The High Court allowed the appeal, holding that the contractual bargain between the parties gave MUR a right to payment in US dollars. Jacobs J reasoned that exercising reasonable endeavours meant endeavours towards the performance of the contractual bargain as agreed between the parties, not to a different result not contained in that agreement. Allowing contractual rights to be varied by considerations of what is reasonable in a case would introduce unwelcome uncertainty into commercial transactions.
The Court of Appeal overturned the High Court’s judgment by a majority, on the basis that:
The Supreme Court unanimously allowed MUR’s appeal, holding that MUR’s rejection of RTI’s offer of non-contractual performance of the contract did not constitute a failure to exercise reasonable endeavours and that, therefore, MUR could rely on the force majeure clause.
In particular, the Court held that:
The Court also distinguished Gravelor Shipping Ltd v GTLK Asia M5 Ltd (2023). This was a summary judgment application following MUR in which the High Court ruled that a party could be required to perform outside its contractual obligations where the imposition of sanctions on a counterparty prohibited performance in the contractually prescribed manner (for further information on Gravelor, see our previous client alert). The ruling was distinguished on the basis that, unlike the general force majeure clause in this case, the sanctions clause in Gravelor:
The Supreme Court has, applying the key English contract law principles of certainty and freedom of contract, introduced further clarity as to how the English courts should restrictively interpret reasonable endeavours provisos in force majeure clauses—an issue that has come very much to the fore in recent years following the unprecedented breadth of sanctions imposed on various Russian entities. This should give commercial parties some comfort that the English courts will uphold their rights to insist on performance of the contract as defined by its terms, absent clear wording to the contrary.
As the judgment makes clear, when seeking to determine whether reasonable endeavours provisos have been met, the parties should consider whether failure to perform contractual obligations can be prevented by taking reasonable steps. For example, in sanctions-related cases, as expressly noted by the Supreme Court, this may include consideration of whether a specific licence could, and should, by reasonable endeavours be obtained from the relevant sanctions authority to overcome the impediment to performance.
Importantly, parties should pay due attention at the contract drafting stage to ensure that their contracts expressly provide for their desired consequences in the event that sanctions issues arise, such as through the inclusion of express sanctions compliance and termination clauses or express terms on alternative methods of contractual performance.
Nafeesa Deen, London Trainee Solicitor, contributed to the drafting of this alert.